- Generators
- Meters
- Maintenance plans
Generator maintenance by run hours: meter readings, thresholds and the calendar
Why diesel generator service should follow the hour meter, not just the calendar: reading routines, "whichever comes first", weekly and monthly checks, the yearly inspection.
· 7 min read
Generator maintenance lives in two different worlds. The standby set at a shopping centre or a cold store may run 30 or 40 hours a year, and the calendar decides when it is serviced. The set at a bakery, a building site or a farm in an area with frequent outages can easily run 100 hours a month, and a yearly service is not enough. Same make, same engine, two different plans.
This guide covers how to tie generator maintenance to run hours: how to read the meter, where to take the threshold from, how to combine the calendar with the hour meter, and where the statutory inspection fits in.
1. Why hours?
A diesel engine’s oil, filters and belts wear as it runs. That is why most manufacturers’ service tables say “every X hours or every Y months, whichever comes first”. X varies from engine to engine; 250 to 500 hours is common, but the right number is in your engine’s manual. Swap the numbers in this post for your own.
The calendar alone goes wrong both ways. On a set that hardly runs, the oil ages before the hours are reached, which is why you still need a yearly service. On a set that runs a lot, 400 hours can pile up in three months, and by the time the “annual service” comes round the engine is two services behind. The answer is to use both.
2. Make the meter reliable
The whole value of hour-based maintenance depends on the readings. A few rules:
- Give readings a routine. Make “Run hours” a required item on the weekly check. Whoever does it, the technician or the site’s own caretaker, reads it off the controller and enters it every week.
- Date every reading. “1,842” on its own says nothing; “14 October, 1,842 hours” does. The difference between two readings shows you monthly use.
- The meter does not go backwards. A reading lower than the last one is either a typo or a replaced controller. The first should be rejected, the second marked as a meter reset. A system that cannot tell them apart lets one typo break the whole plan.
- Track starts as well. A set that runs often for short periods wears its starting system even with few hours. If the controller shows a start count, read it as a second meter.
3. Set the threshold and the lead
An hour-based plan comes down to three values:
- Interval. Every 250 hours.
- Starting point. The reading at the last service. If that was 1,600 hours, the next is due at 1,850.
- Lead. How far before the threshold the work order opens, say 25 hours.
Choose the lead by how fast the set runs. At 5 hours a week, 25 hours is five weeks of warning: enough to order oil and filters and agree a date with the customer. At 40 hours a week the same lead is less than a week, so make it bigger.
Count the next threshold from the reading when the service was actually done, not from the planned value. If the service happened at 1,870 hours, the next is at 2,120, not 2,100. That way each service really covers 250 hours.
4. Combine calendar and hours
A typical routine for a standby generator:
| Job | Interval | Who |
|---|---|---|
| Weekly check | Every week | The site’s own staff |
| Exercise under load | Monthly | Technician or staff |
| Service | Every 12 months or 250 hours, whichever comes first | Service company |
| Periodic inspection | Once a year | Authorised inspector |
Keep the weekly check short: controller in AUTO with no alarms, fuel level, oil and coolant level, block heater working, starter battery voltage, no leaks, run hours. It takes five minutes, but the most useful piece of information, the meter reading, comes from here.
For the monthly exercise, a common reference is the US standard NFPA 110: at least 30 minutes a month at no less than 30% of the nameplate rating. This is not mandatory in Turkey; it is a standard practice, but a good measure against the fuel build-up that light-load running causes (wet stacking). Record load percentage and run time as measurements on the checklist. A monthly run that stays under 30% is a sign that a yearly load bank test is due.
5. The yearly statutory inspection
In Turkey, Annex III of the regulation on health and safety in the use of work equipment lists the periodic inspection of generators as once a year, to be carried out by authorised people from the electrical group registered in EKİPNET (mevzuat.gov.tr). That inspection does not replace maintenance, and maintenance does not replace it. Track their dates separately.
6. Turn readings into work
A reading is worth something only if someone acts when it crosses the threshold. With paper this usually breaks down the same way: the caretaker writes the hours in a logbook, the logbook stays in the generator room, and the service company opens it on the next visit to find it is 300 hours late.
To avoid that, readings have to feed the plan directly. When a reading comes in, the system works out how far the threshold is; once it is within the lead, a work order opens and goes to the service crew. For a two-person company looking after the generators of a few cold stores in Mersin, this means checking a list on screen instead of asking “which site do we need to visit and when?” all over again every week.
7. What the service record should hold
When the service work order closes, record:
- Engine oil changed (with a photo)
- Which filters were changed: oil, fuel, air, water separator
- Coolant, belts and hoses, radiator, exhaust
- Starter battery voltage
- Water and sediment drained from the fuel tank
- Test run done
- Run hours at the time of service
That last item sets the plan’s next threshold. Without the hours on the service record, the plan has nothing to count the next service from.
How this works in Saha
In Saha any unit can have a run hours meter, a start counter or a meter type of your own. Readings come in from the web, from the technician’s iOS or Android app (offline too), when a work order is completed, or in bulk through an Excel import. A new reading cannot be lower than the last one; if the meter was replaced, the reading is marked as a reset.
A maintenance plan uses a calendar trigger, a meter trigger or both, and with both, whichever comes first opens the work order. For a meter trigger you set the interval and how far before the threshold the work order opens; the next threshold counts from the reading at the last service. The generator/UPS template comes with weekly check, monthly load run and service checklists and plans that follow this routine. Template plans arrive switched off, so you adjust the thresholds to your manual and turn them on. The yearly generator inspection is kept as an inspection type in the unit’s history and shows up in the due list as its date approaches.
A quick review
- Is every generator’s hour meter read regularly, with a date?
- Did the service interval come from the engine manual?
- Are calendar and hours used together, whichever comes first?
- Does the lead suit how fast the set runs?
- Does the service record hold the hours at the time of service?
- Is the yearly periodic inspection tracked separately?
Reading a generator’s service date from its own meter rather than the calendar is the simplest way to make sure it runs on the day you need it. Saha is free for 60 days with no card required; create a free account and add your first meter.