- HVAC
- Maintenance plans
- Preventive maintenance
An HVAC preventive maintenance plan: seasonal checks, filters and the calendar
How to set up time-based maintenance for split units, VRF, air handlers and chillers: fixed calendar or from completion, filters, readings and the yearly statutory inspection.
· 7 min read
In most businesses, air conditioning maintenance starts with a complaint. On the first hot day in June a shop calls to say the AC is not cooling. The technician goes out and finds a filter like felt, a blocked drain and an outdoor coil covered in pollen. It is not really a breakdown. It is the service that never happened in April.
This guide covers how a service company, or a business with a few branches, can set up a time-based maintenance plan for its HVAC equipment: which unit gets which interval, how the schedule moves forward, what to look at in a start-of-season check, and where the yearly statutory inspection fits.
1. Split your units by type
“Every AC twice a year” is easy to say, but a wall-mounted split and a hotel’s air handling unit do not need the same service. Start by sorting your equipment into types:
- Split and VRF indoor units, fan coils. The largest group by count. Most of the work is filters, coils and drains.
- VRF outdoor units. Condenser cleaning, electrical connections, compressor current.
- Air handling units and rooftops. Filter pressure drop, belts, fan bearings, dampers.
- Chillers. Water temperatures, pressures, flow switch, oil.
This split is the backbone of the plan, because each type will have its own checklist and its own interval.
2. Pick the intervals and write down where they come from
Most HVAC maintenance intervals come from manufacturers and practice, not from law. Writing that down means you can answer “where did this number come from?” later. A common starting point:
| Unit | Interval | Source |
|---|---|---|
| Split / VRF indoor unit | Every 6 months, at the start of each season | Practice |
| VRF outdoor unit | Every 6 months | Manufacturer |
| Air handler, rooftop | Every 3 months | Practice; shorter if filters load up fast |
| Chiller | Every 3 months or 1,000 run hours | Manufacturer |
| Ventilation and AC installation | Periodic inspection once a year | Regulation (Turkey) |
Compare the practice values with your own equipment manuals. An air handler in a dusty workshop will not last three months on one set of filters. A split in a meeting room used twice a week can easily go six.
3. Fixed calendar or from completion?
In a time-based plan the next due date can be worked out in two ways, and the choice matters.
Fixed calendar. The service happens in the same months every year, say April and October. Even if one visit runs two weeks late, the next one is still in October. For air conditioning this is usually right: the April visit prepares for the cooling season, the October visit for heating. An “April service” done at the end of May should not push the next one into November.
From completion. The next date is counted from the day the last service was done. If a quarterly air handler service runs a month late, the next one moves by a month too. This fits work that depends on use rather than season.
One more rule: decide how far ahead the plan opens the work order. Two weeks is a good start for a seasonal service. If one customer has 40 split units, all those jobs are on screen at the start of April and you can spread them across your crews week by week.
4. What to check at the start of the season
For splits and indoor units, a list you can fill in eight to ten minutes is enough:
- Filters cleaned — checkbox, required, photo required
- Indoor coil clean — pass/fail
- Drain pan and line clear — pass/fail
- Blower clean and quiet — pass/fail
- Return air temperature — measurement (°C)
- Supply air temperature — measurement (°C)
- Outdoor coil clean — pass/fail, photo required
- Compressor current — measurement (A), maximum from the nameplate
- Oil trace or leak sign at joints — yes/no
- Terminals, cables and breaker — pass/fail
- Notes
Record return and supply temperatures separately. In cooling mode the difference is roughly 8–14 K on many units, but that is a rule of thumb and depends on the manufacturer. What really tells you something is how the same unit’s difference changes from visit to visit. If it was 12 K last April and 6 K this April, something is off even with a clean filter.
If item 9 is “yes”, you have a leak check on your hands. Depending on the refrigerant charge, F-gas leak checks also follow statutory intervals, which we covered in our post on refrigeration and F-gas records.
5. Treat filters as their own job
Filters are the most frequent HVAC task and the one most often skipped. A few practical points:
- Close the split filter with a photo. A “cleaned” tick convinces nobody; a photo of a clean filter does. When the customer says “you were here last month and it still smells”, that photo is what you have.
- Measure air handler filters by pressure drop. Make filter pressure drop (Pa) a measurement item and take the maximum from the manufacturer’s final resistance. Over the limit, the filter is replaced. Under it, you do not have to replace it just because the date came round.
- Write down which filter is fitted. A filter with no recorded class or size means someone turns up next time with the wrong part. Keep it as a field on the unit’s record.
6. The yearly statutory inspection belongs in the plan
Maintenance and periodic inspection are different things. In Turkey, Annex III of the regulation on health and safety in the use of work equipment lists the periodic inspection of ventilation and air conditioning installations as once a year. It has to be done by someone from the mechanical group, an engineer, technical teacher or technician registered in EKİPNET, and the installation drawings are checked (mevzuat.gov.tr).
Usually an outside firm does this inspection, not you. Its schedule should still be in your plan: report date, report number, result and next due date. Otherwise the yearly report sits in an email and nobody remembers it in month thirteen.
7. Start the plan small
The typical mistake for an HVAC service company is to tie every unit to every plan on day one. A more useful path:
- Pick the largest type (splits) and the most critical one (a chiller or an air handler).
- Set up one plan for each and run it for a season.
- At the end of the season, look at what ran late: which customer, which crew?
- Then add the other types.
For a five-person company servicing hotels in Antalya, this means seeing in the first two weeks of April which of 300 indoor units will be done at which hotel, by which crew, on which day. Without a plan the same work lines up in the order the customers phone in.
How this works in Saha
In Saha a maintenance plan targets either one unit or every unit of an asset type, optionally limited to one location and everything under it. “All splits at this hotel” is one plan, but each unit keeps its own schedule and gets its own work order. Calendar triggers run in days, weeks, months or years. The next due date is counted either from completion or on a fixed calendar, and a fixed calendar can name months such as April and October. The plan opens the work order by itself as many days ahead as you set, with the work type, priority, assignee or team and checklist taken from the plan. A plan never has more than one open work order per unit.
The HVAC template comes with ready checklists and plans for splits, VRF, air handlers and chillers. Template plans arrive switched off, so you review each one before turning it on. The yearly installation inspection comes as an inspection type: the report, result and next due date land in the unit’s history. Upcoming and overdue maintenance and inspections show in one list. Technicians fill in checklists in the iOS or Android app, with or without a connection.
A quick review
- Are your units sorted into types?
- Is the source of every interval (manufacturer, practice, regulation) written down?
- Are seasonal jobs on a fixed calendar?
- Do filter jobs close with a photo or a pressure drop reading?
- Is the yearly periodic inspection tracked somewhere?
Planning April’s service at the end of March removes most of June’s phone calls. Saha is free for 60 days with no card required, so you can create an account and set up your first plan with your own equipment today.