UPS and battery bank maintenance: periodic checks, internal resistance and replacement planning

What to check on a UPS, how to record its battery bank, why internal resistance is the number to watch, how to plan battery replacement ahead and where the transfer switch fits in.

· 8 min read

Illustration of a UPS cabinet, rows of battery blocks beside it and a reading card with one value marked in orange

A UPS is an odd piece of equipment. For years it seems to do nothing at all, and then it exists for one day. When the mains drop, it carries the load through the seconds or minutes until the generator takes over. If on that day one battery has swollen and two others have gone weak, the server room, the operating theatre or the tills go dark anyway, and the green light on the front panel was still saying “all good” the day before.

This guide covers how to tie UPS and battery bank maintenance to a proper record: how to register the unit and its batteries, what to check at the six-monthly service, how to plan battery replacement ahead of time and where the statutory inspection fits. Generator maintenance by run hours has its own guide, so we will not repeat it here.

1. Record the UPS and the batteries separately

The first decision is simple but shapes everything after it: the UPS is one asset, the battery bank is another, recorded underneath it. The reason is that they live for different lengths of time. A UPS can run for ten years or more; in common practice VRLA batteries last 3 to 5 years in service. When the batteries are replaced, the UPS keeps its history, but the batteries get a new installation date.

Fields worth keeping on the UPS:

  • Rated power (kVA)
  • Topology: online double conversion, line interactive or offline
  • Phase configuration: input/output 1/1, 3/1 or 3/3
  • Bypass type: internal or an external maintenance bypass
  • Parallel operation, yes or no

And on the battery bank:

  • Battery type: VRLA AGM, VRLA gel, flooded or lithium-ion
  • Block voltage and block count, for example 40 blocks of 12 V
  • Capacity (Ah)
  • Installation date of the batteries
  • Design life (years)

The last two are the basis of the replacement plan below. Nobody can tell you when a battery bank is due for replacement if nobody knows when it was installed.

On sites with a generator the same logic applies to the automatic transfer switch (ATS): it is recorded as a sub-asset of the generator, with its rated current and transfer type (contactor, motorized breaker or static).

2. What to check at the six-monthly UPS service

Most manufacturers recommend one or two services a year; six months is a common starting point for critical loads. If your unit’s manual asks for more, follow the manual. A ten-minute check covers:

Item Kind Note
Event log reviewed Tick, with photo What happened since the last visit
Input voltage Measurement
Output voltage Measurement 207–253 V
Load Measurement At most 80% (practice)
Battery string voltage (float) Measurement
Lowest block voltage Measurement Limit from the manufacturer
Highest internal resistance Measurement Against the baseline
Swelling / leakage / corrosion Pass / fail, with photo
Fans and air filters Pass / fail
Room temperature Measurement At most 25 °C
Bypass transfer test Pass / fail

A few of these deserve a word on why:

  • Event log. The UPS keeps its own history: how often it went to battery, how often it fell back to bypass, which alarm came when. A photo of the screen answers “what happened during that outage?” six months later.
  • Load. 80% is not a legal limit but a working practice. It leaves headroom on the unit and catches the day someone adds a rack or a new machine and quietly pushes it into overload.
  • Room temperature. VRLA battery life is rated at 20 to 25 °C. The life on the label is no promise for a battery that sits in a warmer room. One summer with a broken air conditioner can take a year or two off a battery bank, so write the temperature down as a number at every visit.

3. The number that matters: internal resistance

The total string voltage can look normal on float for a long time while the batteries are already going. When a block is heading for failure, its internal resistance is often the first thing to change. So:

  • Measure the internal resistance of every block when the batteries are installed, or at the first service, and keep it as the baseline.
  • At every service, record the highest block’s internal resistance and the lowest block voltage.
  • When internal resistance rises 25% above the baseline, consider replacing the batteries.

A single reading says little; the value is in the line over the years. When the readings stay on a paper form, the line is lost with them. We wrote about setting up checklists with measurements in a separate guide.

4. Plan battery replacement ahead

Replacing a battery bank is not a small job. For a 40-block string you need a budget, an order, a delivery date and a window to swap the batteries without dropping the load. Finding that out after a failure is the most expensive way.

A practical rule: set the reminder at the installation date plus 80% of the design life, and open the job two months before. For a bank installed in March 2024 with a 10-year design life, 80% is eight years: the reminder falls in March 2032 and the job opens in January 2032. Treat this as a ceiling. If internal resistance or an autonomy test points to an earlier replacement, follow the measurements; in a hot room or on a site with frequent outages that happens often.

When the batteries are replaced, update the installation date on the battery bank, measure a new internal resistance baseline for the new blocks, and record the batteries used on the work order as parts.

5. The transfer switch and the monthly test

A UPS is there to bridge a short gap; in a long outage the generator takes the load. Between them sits the transfer switch, and it cannot be trusted without being tested either. During the generator’s monthly exercise under load, a mains failure is simulated, the ATS transfer is tried and the transfer time is measured. The US standard NFPA 110 aims for 10 seconds on emergency power systems. It is not mandatory in Turkey, but it is a useful yardstick, and the UPS autonomy should cover that time with plenty to spare.

6. The statutory inspection

In Turkey, Annex III of the regulation on health and safety in the use of work equipment lists the periodic inspection of accumulators (batteries) as once a year, carried out by people from the electrical group or chemical engineers registered in EKİPNET (mevzuat.gov.tr). Treating a UPS battery bank as an accumulator under that item is an interpretation, so confirm it for your own site with your occupational safety specialist and the inspection company. The UPS output wiring falls under the yearly electrical installation inspection; we covered how to record that in the electrical panels guide.

Under the same regulation, maintenance and repair records are kept for the whole service life of the equipment, and periodic inspection reports for as long as the equipment is in use. Ten years of a UPS’s service history should be readable from one record, not from a folder of service sheets.

How this works in Saha

The Generators/UPS template in Saha comes with asset types for UPS units, battery banks, transfer switches, diesel and gas generator sets and external fuel tanks, with the fields listed above. A battery bank is recorded as a sub-asset of its UPS, and a transfer switch as a sub-asset of its generator. The template includes a UPS maintenance checklist that matches the table above and a UPS maintenance plan that runs every six months. Measurement items carry their limits (output voltage, 80% load, 25 °C room), and an answer outside them is flagged. Template plans arrive switched off, so you adjust the interval to your manual and turn them on.

For battery replacement, the “Battery replacement” work type and the “Batteries” part category are ready. You set up the replacement reminder as a plan for that battery bank: work out the first due date from the installation date and design life, enter it, and the plan opens the work order as many days ahead as you choose. The yearly battery inspection comes as an inspection type: the report, result and next due date sit in the battery bank’s history, and upcoming inspections show in the same list as maintenance.

Technicians fill in checklists in the iOS or Android app, with or without a connection. Fault types such as “UPS on bypass”, “Battery fault / low runtime” and “UPS overload” are included, and staff on site can report a fault from the QR label on the unit.

A quick review

  • Are the UPS and its battery bank recorded as separate assets?
  • Are the battery installation date and design life written down?
  • Is there an internal resistance baseline, and is it measured at every service?
  • Is the UPS room temperature recorded as a number?
  • Is there a dated reminder for battery replacement?
  • Is the yearly battery inspection tracked separately?

A UPS earns its keep in the few minutes of an outage, and those minutes are decided by readings taken months earlier. Saha is free for 60 days with no card required; create a free account and add your first UPS and its batteries.